Belgium | HoWest | 11 kWe | 1 | 2011 | Test unit for simulation and R&D in UGent University |
Belgium | Proviron | 250 kWe | 1 | 2011 | Recovery of waste heat from LP steam in chemical plant. Additional savings on steam condensate. |
Belgium | Vanheede | 55 kWe | 1 | 2012 | Recovery of jacket water in biogas plant. |
Germany | Holzheizkraftwerk | 90 kWe | 1 | 2013 | Recovery of heat excess in district heating. Heat delivered by biomass boiler (wood). |
Norway | Alstom | 90 kWe | 1 | 2013 | Recovery of heat from exhaust gases in anode baking furnace through Alstom’s patented heat exchanger. |
Germany | Holzheizkraftwerk | 315 kWe | 1 | 2014 | Recovery of heat excess in district heating. Heat train with biomass boiler, high temperature ORC and district heating with E-Rational ORC. |
Belgium | Delta Thermic | 22 kWe | 1 | 2014 | Heat recovery to electricity combined with heating of public swimming pool at ORC cold side. Heat delivered by wood chip boiler. |
Japan | Tokyo Sangyo | 260 kWe | 1 | 2014 | Power production with geothermal heat. Delivery of first machine in project. |
Japan | Tokyo Sangyo | 260 kWe | 2 | 2015 | Power production with geothermal heat. Delivery of 2 additional machines on same project as previous. |
Belgium | Beneens | 110 kWe | 1 | 2016 | Recovery of heat from biomass boiler (wood). Cold side of the machine is connected to the local heating network. |
UK | Dordtech | 90 kWe | 1 | 2015 | Recovery of waste heat from a biomass boiler. The cooling side of the ORC is used for low temperature drying processes. |
France | TREDI | 370 kWe | 2 | 2016 | Recovery of waste heat from industrial waste incinerator. |
UK | Dordtech | 110 kWe | 1 | 2016 | Recovery of waste heat from a biomass boiler. The cooling side of the ORC is used for low temperature drying processes. |
Romania | Energy Serv | 200 kWe | 1 | 2016 | Recovery of waste heat from wood fired boiler. E-RATIONAL ORC connected to cooling side of a Turboden high temperature ORC. |
UK | Crossfieds Farm | 220 kWe | 1 | 2016 | Recovery of waste heat from biomass boiler. The cooling side is used for drying processes. |
UK | Stuart skelton | 160 kWe | 1 | 2016 | Recovery of waste heat from biomass boiler. The cooling side is used for drying processes. |
South Korea | LSIS Gyeongsannam | 160 kWe | 1 | 2016 | Recovery of waste heat in the form of steam into electrical power. |
UK | IEC Solutions | 220 kWe | 1 | 2016 | Recovery of waste heat from biomass boiler. The cooling side is used for drying processes. |
UK | Tudor Griffits Group | 185 kWe | 2 | 2016 | Recovery of waste heat from biomass boiler. The cooling side is used for drying processes |
UK | Barden Biomass | 180 kWe | 1 | 2016 | Recovery of waste heat from biomass boiler. The cooling side is used for drying processes |
UK | Isembard Ltd | 90 kWe | 1 | 2016 | Recovery of waste heat from biomass boiler. |
UK | Barden Biomass | 90 kWe | 1 | 2016 | Recovery of waste heat from biomass boiler. The cooling side is used for drying processes. |